Wednesday, July 11, 2007

keep up your spirits


New hurdles appearing every day.
I tell myself the phases when you regret having started are the hallmarks of a successful project. Progress photos click here (same album as below but we update it).


So far we have had:
  • first digger was too small and could not progress fast enough
  • second (needed smashing down wall) was too large to move around properly in the garden
  • third digger was the right size but seems not available when needed (think we had 4 kinds of diggers so far)
  • digging area originally estimated has increased from 13m to 15m (because of a mistake) and from there to about 18m (having forgotten to account for length of joints between each collector) taking us right to the edge of the stairs
  • falling over of dumpers, causing some minor delays
  • powerful dumper broke engine after falling over and has been there and irremovable for a week
  • heat pump came with damaged door
  • joints (between all the collector panes) supplied were the wrong size
  • the digging contractor walked out from the job, he gave up and left (without being paid)
  • not enough space to put all the soil so collectors have to be put in and tested in phases making job more complex and time consuming
  • also the little space and the wrong estimates means that branches of apple tree are being damaged by the diggers
  • after old loft tanks were removed and new pipes wired up we had a water leak from the loft through to our bedroom and into the ground floor sitting room